    <fulldesc>&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;&lt;strong&gt;New Delhi, Nov 18 (KNN)&lt;/strong&gt; In a significant judgment, the National Company Law Appellate Tribunal (NCLAT) New Delhi has ruled that interest on the principal amount cannot be claimed unless explicitly provided for in the agreement.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;The decision was delivered by Justice Ashok Bhushan (Chairperson) and Barun Mitra (Technical Member) in the case of M/s Vedic Projects Pvt. Ltd. vs. Shri Sutanu Sinha.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;The tribunal emphasised that contractual terms take precedence, and in the absence of an interest clause, claims for delayed payment interest cannot be entertained.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;The bench also clarified that issues arising under Section 16 of the MSMED Act, which allows for interest on delayed payments to MSMEs, cannot be adjudicated by the National Company Law Tribunal (NCLT) or NCLAT, as these tribunals are not the appropriate forums for such matters.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;The dispute arose during the Corporate Insolvency Resolution Process (CIRP) against M/s Simplex Projects Ltd., initiated on April 27, 2022, following an application by the State Bank of India.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;The appellant, M/s Vedic Projects Pvt. Ltd., an operational creditor, claimed Rs 23.42 crore, which included the principal amount and interest accrued as per the MSMED Act.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;The claim stemmed from a sub-contract agreement dated June 16, 2010, for construction work related to the Kabrai Feeder Channel in Uttar Pradesh.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;Bills totalling Rs 41.54 crore were raised between 2010 and 2014, with Rs 10.36 crore remaining unpaid. While the Resolution Professional (RP) admitted the principal claim of Rs 10.36 crore, the demand for interest was rejected due to the absence of an interest clause in the agreement.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;The appellant argued that as a registered MSME, it was entitled to interest on delayed payments under Section 16 of the MSMED Act. They contended that the Corporate Debtor had delayed payment since 2016, warranting additional interest.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;The tribunal reviewed the sub-contract agreement and found no provision for interest on delayed payments. It upheld the RP's stance and ruled that the principal amount alone could be admitted.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;It also underscored that the MSMED Act claims for interest are outside the purview of insolvency tribunals.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;This judgment serves as a precedent for operational creditors, stressing the necessity of incorporating clear contractual terms regarding interest in agreements.&lt;/span&gt;&lt;/p&gt;&#13;
&#13;
&lt;p&gt;&lt;span style=&quot;font-size:14px&quot;&gt;&lt;em&gt;&lt;strong&gt;(KNN Bureau)&lt;/strong&gt;&lt;/em&gt;&lt;/span&gt;&lt;/p&gt;&#13;
</fulldesc>
    <id>39954</id>
    <link>https://knnindia.co.in/news/newsdetails/msme/nclat-rules-no-interest-on-principal-in-absence-of-contractual-provision</link>
    <pubDate>2024-11-18 17:01:14</pubDate>
    <source>knnindia.co.in</source>
    <title>NCLAT Rules No Interest on Principal in Absence of Contractual Provision</title>